How much unsafe cladding has been fixed?
Nine years after Grenfell, thousands of blocks of flats still have unsafe cladding. As a new bill to force owners to act is debated, here is what the progress figures do and do not show.
How far has England got in removing unsafe cladding from blocks of flats, and what would the new bill change?
Part 1
What this is about
Cladding is the outer skin fixed to the walls of a building. In June 2017 a fire spread up the cladding of Grenfell Tower in west London and 72 people died. Checks afterwards found that thousands of other blocks of flats in England had outer walls that could let a fire spread in the same way.
Fixing a building means stripping off the unsafe material and replacing it, which can take months or years and cost millions of pounds per block. Until the work is done, residents may live with fire wardens on patrol, higher insurance bills and flats they cannot easily sell or remortgage.
The government's latest monthly figures, to the end of August 2026, track 4,724 buildings of 11 metres or taller (about four or five storeys and up) known to have unsafe cladding. Work has been finished on 1,849 of them, about two in five. Nearly half, 2,153, have not started. The government's best estimate is that between 5,900 and 7,400 such buildings exist, so some have still not been found.
Finding every affected building takes surveys, and the government says some owners have been slow to act; its new bill targets these "blockers". Since 2022 the law has shielded most leaseholders in taller blocks from most of the bill.
It is in the news because the government's new Building Safety (Remediation of Unsafe Cladding etc) Bill has its first full Commons debate (second reading) today, 27 October 2026. It would put a legal duty on building owners to fix unsafe cladding, with fines of up to £500,000 for ignoring a tribunal's order to do the work. The next monthly progress figures are due on 28 October.
4,724
buildings 11m+ known to have unsafe cladding
MHCLG monthly data, end of August 2026
46%
of those have not started work
MHCLG monthly data, end of August 2026
£15.1 billion
central estimate of the total cost of the work
MHCLG estimate as of March 2025 (range £11.8bn to £22.7bn)
Explainers
The same story in the format that suits you: watch it, listen to it, or take it in at a glance.
Nine years after Grenfell, flats with unsafe cladding are still being fixed. You hear progress figures. Here's what they mean.
Part 2
What's being said
“Over 470 more buildings are reported to have completed cladding remediation since the Remediation Acceleration Plan was published”
Ministry of Housing, Communities and Local Government (press release quoting Building Safety Minister Baroness Blake) · 14 October 2026
GovernmentHow it was used
Used in the press release announcing the new bill, as evidence that the government's December 2024 plan had sped up the work.
How it could mislead
A count of extra completions says nothing about how many buildings are still waiting, and the published series changed method in December 2025.
What the figures say
Completed buildings rose from 1,463 (November 2024) to 1,849 (August 2026) in the published tables. The tables are not directly comparable across December 2025. Meanwhile 2,153 known buildings had not started.
“Only 38% of buildings have completed remediation, 16% have started and 47% have not begun at all”
Baroness Sanderson of Welton, Conservative frontbench, House of Lords
ConservativeSource neededHow it was used
Said in the Lords debate on a Liberal Democrat bill on leaseholder costs, to argue that remediation has been too slow.
How it could mislead
The shares count only buildings already identified. Buildings not yet found are left out, so the share of the whole problem left to fix is larger.
What the figures say
The figures match MHCLG's June 2026 release (4,469 monitored buildings). The July release, out by then, showed 39%, 15% and 46%. Wording taken from a mirror of Hansard, not the Hansard page itself.
“The estimate from the Commons' Public Accounts Committee is that 3 million people may be affected”
Baroness Pinnock, Liberal Democrat housing spokesperson, House of Lords
Liberal DemocratSource neededHow it was used
Said when opening the Lords debate on her own bill, which would extend cost protections to leaseholders in buildings of any height.
How it could mislead
It could be read as 3 million people living in unsafe blocks. The committee's figure is an upper limit for everyone affected by the crisis, including through costs and sales.
What the figures say
The Public Accounts Committee (March 2025) wrote that the crisis may have affected up to 3 million people. It gave no breakdown of how they were affected.
Part 3
What the figures show
What the progress figures show
At the end of August 2026, work had started or finished on 2,571 of the 4,724 monitored buildings (54%), and 1,849 (39%) were finished, including some still awaiting final sign-off. Taller blocks are further ahead. Work had begun on 62% of buildings of 18 metres and over, against 46% of those between 11 and 18 metres. In the government's Cladding Safety Scheme, only 28% had started or finished.
The monitored list is not the whole problem. The government's own estimate implies it holds 65–81% of the buildings expected to need work. Set against that larger total, the 1,849 finished buildings are roughly a quarter to a third of the job (our calc).
Buildings 11m+ in England, end of August 2026
What it costs and who pays
The government estimated in March 2025 that the work would cost between £11.8 billion and £22.7 billion, with £15.1 billion as the central figure. It says £9.2 billion is available: £5.2 billion from the Treasury, about £0.7 billion in refunds from developers and £3.4 billion it aims to raise from the Building Safety Levy on new homes, which began on 1 October 2026.
Large developers pay for buildings they built under a contract with the government. By the end of August 2026, 53 had signed, and their 2,679 buildings have an estimated repair cost of around £4.2 billion. Other costs fall on building owners and, where the 2022 protections do not reach, on leaseholders. Buildings under 11 metres sit outside most of those protections.
Deadlines, and what independent bodies found
In December 2024 the government published a Remediation Acceleration Plan. In July 2025 it set deadlines: owners of buildings of 18 metres and over must finish by the end of 2029, and those of 11 to 18 metres by the end of 2031, or face unlimited fines or prison.
The National Audit Office, which checks government spending, said in November 2024 that the government's modelling pointed to 2035 before all work was complete, and that up to 60% of affected buildings had not been identified. It used an older estimate of 9,000 to 12,000 buildings, since revised down to 5,900 to 7,400. In March 2025 the Commons Public Accounts Committee called the plan's target dates "unconvincing" and said the crisis may have affected up to 3 million people.
What the parties propose
The Labour government's bill would give building owners a legal duty to assess and fix unsafe outer walls, let councils ask a tribunal to step in when owners fail, create a register of 11 to 18 metre blocks and make it easier to claim costs back from cladding makers. The government says it will help around 12,000 residents more quickly.
Baroness Pinnock, the Liberal Democrats' housing spokesperson in the Lords, has a bill that would protect leaseholders from the cost of a wider set of defects, such as unsafe balconies, in buildings of any height, with set time limits for the work. In the Lords debate the Conservative frontbench criticised the pace of remediation. No published Conservative or Reform UK position on the new government bill was found before today's debate.
The other side
- Taller blocks are further ahead Work has begun on 62% of buildings of 18 metres and over. The slowest progress is in the Cladding Safety Scheme, where 28% have started or finished.
- The list keeps growing New buildings join the monitored list each month as surveys find them, which pulls the completion rate down even while more work is being finished.
- Counting changes cut both ways Social housing was counted differently from December 2025, so the published series cannot simply be compared across that date. That makes the government's 470 hard to check, and the raw tables may understate progress.